Anglo Approves $1.2B Barro Alto Nickel Project

JOHANNESBURG (I-Net Bridge) -- Global resources group Anglo American plc [Nasdaq:AAUK; LSE:AAL] has announced the approval of the Barro Alto nickel project in Brazil, at an estimated capital cost of $1.2 billion.

The production from Barro Alto will contribute significantly to a potential doubling of the group's nickel production to around 90,000 tonnes per annum by 2011, said Anglo CEO Tony Trahar said in a statement on Thursday.

Barro Alto will produce an average of 36,000 tonnes of nickel per year in the form of ferronickel over a minimum 26 year mine life. Construction of the Barro Alto facilities is scheduled to begin in 2007 with production commencing in 2010 and ramping up to full capacity during 2011, Anglo said.

Barro Alto is located in the state of Goias in Brazil, about 170 kilometers north-west of Brasilia, 240km north of Goiania and 150km from Anglo American's existing Codemin nickel operation.

The Barro Alto nickel deposit was discovered in the late 1960s and Anglo American completed its purchase of the deposit for $35 million in 2002. A feasibility study was initiated in 2004 and completed in September this year.

The deposit contains resources of 116.2 million tonnes, at an average grade of 1.54% nickel, of which 62.4 million tonnes at an average grade of 1.66% nickel will be mined by conventional open pit methods and treated over a 26 year period.

Part of the Barro Alto deposit is currently being mined to feed Anglo American's Codemin plant in Niquelandia, Goias. Ore from Barro Alto is trucked to Codemin for processing in the existing facilities. This has successfully extended the life of Codemin and permitted an increase in production from 6,000 to 10,000 tonnes per annum, allowing Codemin to benefit further from the strong nickel price, the group said.

Barro Alto ore will continue to be transported to Codemin throughout the life of the newly approved Barro Alto project. The experience gained in mining and treating Barro Alto ore at Codemin significantly reduces the technical risk of the project, Anglo added.

The construction of Barro Alto will include extending the existing open pit mine operation and constructing a new ferronickel smelter and refinery. A long term power supply has been secured. The operation will use tried and tested technology currently used by Anglo American at Codemin and Loma de Niquel in Venezuela.

"The Barro Alto project is an exciting greenfield project in a country where Anglo American has longstanding nickel project management and operating experience," said Trahar.

"The outlook for the nickel market is positive with strong demand continuing and this project provides an excellent opportunity to grow Anglo American's position in this attractive market," he concluded.

(c) Copyright 2006 I-Net Bridge. All rights reserved. I-Net Bridge, Tel: +27-11-280-0644 newsdesk@inet.co.za.

Comments

Free Daily eNewsletter

Sign up to receive Resource Investor's FREE Newsletter.

Futures Magazine

Futures, Options, Stock, Forex and Derivative Strategies, Analysis and News

Visit FuturesMag.com
Recent News